DILR Set 4: Network Dependency

Tasks A, B, C, D, E. Dependencies: A->B, A->C, B->D, C->D, D->E.

Question

Updated
DILR Set 4: Longest path duration if A=2, B=3, C=4, D=2, E=1? (Q1)